Guizhou Nayong Longqing Wujiang Cement
2500t/d Cement Clinker Production Line WHR Project
This is a 2500t/d cement clinker line
equipped with WHR unit in EPC construction mode. It’s equipped with 2 boilers
and 1 turbine. Turbine& generator’s power capacity is 5MW. The construction
period is 9 months. The project is started on 5th August, 2013 and realized
with electricity generating on 21st, April. On 24th July, the project passes
the performance test.