Yinan Zhonglian Cement 4500t/d Clinker Production Line 9 MW WHR Project
This is a 4500t/d clinker production line equipped with WHR unit in EPC construction mode. The unit is designed with 2 boilers and 1 turbine. Turbine& generator’s installed power capacity is 9 MW. The total construction period is 230 days. The project is actually started on 18th November, 2012, and realized with electricity generating on 17th October. The unit passes the performance test on 20th December.