This project is a 2500t/d cement clinker production line equipped with WHR project in the EPC construction mode. It’s designed with 2 boilers and 1 turbine. Generators’ installed power capacity is 4.5MW. The total construction period is 10months. The project is actually started on 1st, July, and combined to grid on 24th April, 2013. On 5th June, this project passes the performance test.