This project is a 4500t/d clinker production line equipped with a WHR unit in the EPC construction mode. It’s designed with 2 boilers and 1 turbine. The generators’ installed power capacity is 9MW. And the total construction period is 10 months. The project is started from 12th, 2010, and on realized with electricity generating on September 2011. Through numerous performance tests, the electricity has met the target stipulated in the contract.