On October, 31,
2014, 02:37 a.m. local time, the 7.5MW WHR station of ASLAN CEMENT (TURKEY)
3,750t/d clinker production line, undertaken by Shanghai Triumph Energy
Conservation Engineering Co., Ltd. as its general contractor, was successfully
combined to grid at the first time.
ASLAN project is the first
overseas WHR project signed by Shanghai Triumph that involves seawater cooling
and is added with an isolated power system operation mode. Since the signing of
project contract, there have been the turnover of the cement plant’s top
management, the alteration of the construction scheme, the change of the
installation company, etc., however, ASLAN project team has always upheld its
conviction of persistence and its rigorous and responsible working attitude,
and continuously adjusted its measures to local conditions according to the
changes during field construction, thus to provide rational and effective
instructions and do all the detailed work in terms of progress, quality and
safety.
The client of ASLAN project
highly praised the “refined management” provided by Shanghai Triumph in
executing the contract of the project, and said that the successful combination
to grid of the project on schedule is inseparable from the professional
expertise and exquisite technologies of the highly-responsible and high-quality
ASLAN project team of Shanghai Triumph. Currently, all the staff of ASLAN
project team are still sticking to the frontline of the unit, and they will
dedicate themselves to preparing for project performance assessment, completing
project acceptance and signing the PAC certificate at an early date.